The Authority of The Borough of Charleroi may be working in your area in order to make improvements to the water and systems.
The Authority asks for your cooperation with parking and to use caution when traveling thru the work areas during construction. During this time, every effort will be made to keep service interruptions to a minimum. Notice will be given prior to any service interruptions except for emergencies.
PLEASE DIRECT ANY QUESTIONS TO THE AUTHORITY OFFICE AT 724-483-3585
CURRENT WATERLINE PROJECTS:
STATE STREET – SPEERS / WATERLINE REPLACEMENT
STATUS: WORK UNDERWAY
APPROXIMATE START DATE: CONSTRUCTION STARTING SEPTEMBER 2, 2025
DESCRIPTION: INSTALLATION OF 3100 FEET OF 6-INCH WATERLINE FROM MAPLE DRIVE IN SPEERS TO CHERRY LANE IN TWILIGHT
CLICK HERE TO VIEW MAP OF WORK AREA
PITTSBURGH ROAD – BENTLEYVILLE & SOMERSET TOWNSHIP / WATERLINE REPLACEMENT
STATUS: HIGHWAY OCCUPANCY PERMIT ISSUED / CONTRACT AWARDED, AWAITING SIGNATURES
APPROXIMATE START DATE: TO BE DETERMINED
DESCRIPTION: INSTALLATION OF 1500 FEET OF 8-INCH WATERLINE FROM THE PITTSBURGH ROAD VAULT TO AMES ROAD.
CLICK HERE TO VIEW MAP OF WORK AREA
CURRENT SEWAGE PROJECTS:
6TH STREET – CHARLEROI / SEWAGE LINE REPLACEMENT
STATUS: WORK UNDERWAY
APPROXIMATE START DATE: SEPTEMBER 8, 2025
DESCRIPTION: INSTALLATION OF APPROXIMATELY 540 FEET OF 12-INCH SANITARY SEWER LINE BETWEEN LINCOLN AVENUE AND CREST AVENUE
CLICK HERE TO VIEW MAP OF WORK AREA
COMBINED SEWER OVERFLOW (CSO) / PHASE II WORK
STATUS: DESIGNED, READY FOR BIDDING / AWAITING R.U.S. APPROVAL
APPROXIMATE START DATE: TO BE DETERMINED
DESCRIPTION: NEW PUMP STATION AT MAPLE CREEK NEAR WESTERN FLOUR, NEW PUMP STATION NEAR THE SEWAGE PLANT, UPGRADES TO THE MAPLE CREEK AND LOCK 4 LIFT STATIONS, INSTALLATION OF FORCE MAIN FROM MAPLE CREEK TO THE SEWAGE TREATMENT PLANT.
CLICK HERE TO VIEW MAP OF WORK AREA
OTHER INFRASTRUCTURE IMPROVEMENT PROJECTS:
WATER FILTRATION PLANT / EMERGENCY GENERATOR
STATUS: WORK UNDERWAY / START-UP AND TETSTING SCHEDULED
APPROXIMATE START DATE: JULY 2024
DESCRIPTION: INSTALLATION OF AN EMERGENCY GENERATOR, TRANSFER SWITCH, AND ASSOCIATED ELECTRICAL INFRASTRUCTURE THAT WILL PROVIDE EMERGENCY BACKUP POWER TO THE ENTIRE WATER FILTRATION PLANT.
CEMETERY STREET PUMP STATION
STATUS: PUMPS AND DRIVES INTALLED AND IN SERVICE
DESCRIPTION: REPLACEMENT OF PUMPING AND ASSOCIATED ELECTRICAL EQUIPMENT
FUTURE PROJECTS:
MARIE DRIVE – FALLOWFIELD TWP. / WATERLINE REPLACEMENT
STATUS: DESIGN COMPLETE
APPROXIMATE START DATE: TO BE DETERMINED